The Todd County Elementary School was completed on August 15th and was ready for 650 kids grades K-5. First day of classes was August 26th.
Structural steel, hollow core plank, and architectural precast panels are being erected to form the shell on the new addition to the Coca Cola project. Crews are working to enclose the addition before the end of October. Interior framing and rough in work are taking place within the existing space remodel area.
Crews continue to set precast stair tower and elevator shaft.
Setting Precast wall panels to connect the new Crow Peak Hall to the existing Heidepriem Hall.
DKC crews have the first floor prep ready for the concrete pour.
DKC crews are placing the first floor of the new Crow Peak Hall.
GBK Joint Venture; provides TECTUM Acoustical sound treatment for the walls and ceiling baffles of the CATM Indoor Firing Range, Ellsworth AFB SD. A design/build performance contract issued to our team for the reduction of sound reverberations inside the facility while in use for training activities.
Crews work to complete the site work on the new Todd County Elementary School schedule for an August 15, 2014 completion. The interior of the facility is on track to meet the scheduled completion date. The photo depicts a typical classroom at the facility.