Precast wall panels and structural steel are near complete to enclose the new addition on the Coca Cola Addition project. The north face of the project will be a clerestory with full height exterior glass wall and open from first floor up through the second floor. Interior framing and rough-in work continues on the project. The new 5,000 square foot office addition is scheduled for completion in April 2015.
The masons have begun to place the brick veneer at the Northeast corner of the building and were working towards the west up to the bend of the building at Grid ‘W’.
Site work associated with the pedestrian bridge is ongoing. The third column has been poured. The abutment walls will follow.
Black Hills Steel Erectors are continuing steel and precast erection at the commons areas (P-West). Reinforcing steel for the concrete floor topping is being placed and the floors will be poured as soon as possible.
The mechanical contractor has installed some of the ventilation mains on the third floor. As the ducts are installed the ends are sealed as required by LEED IEQ Credit 3.1: Indoor Air Quality During Construction.
MQ-9 Bunker Roof Replacement, EAFB SD. GBK Joint Venture crew has completed the waterproofing replacement system for the roof of an underground vault. All existing waterproofing membranes were excavated and exposed, and a multiple series of new materials was installed to replace the others which had failed.
Work continues on the new parking lot for the Burger King on East North Street in Rapid City.
Work continues on the exterior steel stud framing on Crow Peak Hall. The framers had the challenge of figuring out how to stand 54’ long steel studs on the exterior of the building. They are making good progress as the bulk of the north side of the building is complete, with window framing left to be completed.
Demolition work has begun on the Ft. Meade Surgical Tower.