Crow Peak Hall, Black Hills State University, Spearfish, SD 2/13/15

Progress is being made on the exterior of the building as the masonry continues. Progress is being made on the exterior of the building as the masonry continues.
The pedestrian bridge footings are complete and work has started on the wing walls.

The pedestrian bridge footings are complete and work has started on the wing walls.
Footings are being formed on the Amphitheater area.
Footings are being formed on the Amphitheater area.

Work is continuing on the wing walls for the pedestrian bridge.


Work is continuing on the wing walls for the pedestrian bridge.
Read More
blog image

RESPEC Interior Remodel, Rapid City, SD 2/6/2015

Interior Office and Bathroom renovation at Respec, Jet Dr. Rapid City.  All construction work is being coordinated around normal business activity.  The completion of the initial Mid-Level Bathroom stage one is on schedule for turn-over, enabling demo work to begin soon for the Upper Level Kitchen area.   


Read More
blog image

Coca-Cola Administrative Area Renovation and Addition 1/19/15

The building envelope is enclosed sufficient enough to allow interior finish work to begin in certain areas of the project. Metal stud framing and gypsum wallboard continue to be installed as well as mechanical and electrical rough in work. Interior walls are being taped, textured, and painted. The curtain wall glass is schedule for arrival on the project the week of January 12th which will fully enclose the building addition upon installation.



Read More
blog image

Surgical Tower Addition, Ft. Meade, Sturgis, SD 1/7/15

Foundation wall construction will be 100% complete next week.
 
Read More
blog image

Coca-Cola Administrative Area Renovation and Addition 12/11/14

Precast wall panels and structural steel are near complete to enclose the new addition on the Coca Cola Addition project. The north face of the project will be a clerestory with full height exterior glass wall and open from first floor up through the second floor.  Interior framing and rough-in work continues on the project. The new 5,000 square foot office addition is scheduled for completion in April 2015.

Read More
blog image

Crow Peak Hall, Black Hills State University, Spearfish, SD 11/21/14

The masons have begun to place the brick veneer at the Northeast corner of the building and were working towards the west up to the bend of the building at Grid ‘W’.

Site work associated with the pedestrian bridge is ongoing. The third column has been poured. The abutment walls will follow.

Black Hills Steel Erectors are continuing steel and precast erection at the commons areas (P-West). Reinforcing steel for the concrete floor topping is being placed and the floors will be poured as soon as possible.

The mechanical contractor has installed some of the ventilation mains on the third floor. As the ducts are installed the ends are sealed as required by LEED IEQ Credit 3.1: Indoor Air Quality During Construction. 

Read More
×