Precast bridge work underway at Crow Peak Hall.
Wing walls on the southeast side of the pedestrian bridge are complete and crews will now be moving to the northwest side.
Excavation has begun for the volleyball pit. DKC crews will begin installing volleyball poles, nets and boundary lines in conjunction with the sand placement.
Picture from the 4th floor of the building overlooking the BHSU campus and site activities. Work continues on the Amphitheater tiered concrete seating as well as the pedestrian bridge foundations and wing walls.
Concrete terrace walls continue for the future amphitheater seating area.
The basement floor has been completed and work continues on the first slab on deck.
The netting serves two purposes: it is designed to be debris netting to catch falling concrete debris from the wind damaged roof, it will also double as fall protection for the contractor whom replaces the damaged roof structure in the future.
Work is continuing on the wing walls for the pedestrian bridge.