Posts for 2015

Surgical Tower Addition, Ft. Meade, Sturgis, SD 9/24/15

 – By

Rubber roofing material being installed.

Read More

Last Modified:


Sanford Homestake CASPAR Laboratory, Lead, SD 6/26/15

 – By

Dean Kurtz Construction is working on construction of the Borated Polyethylene Shielding mazes which are designed to block the trajectory of neutrinos from room to room while still allowing electrical, plumbing, fire sprinkler, and HVAC systems to pass through! Our subcontractors continue work on installing their systems with in the CASPAR cavern as well as the BHSU Cleanroom space.

Read More

Last Modified:


Surgical Tower Addition, Ft. Meade, Sturgis, SD 6/3/15

 – By

Structural steel and masonry work in progress.



Read More

Last Modified:


Sanford Homestake CASPAR Laboratory, Lead, SD 5/15/15

 – By

DKC is working on finishing up refinishing the floor and installing door frames while WD Masonry follows behind installing concrete masonry walls. Also, Rocky Mountain Clean Rooms is installing the hard-wall modular cleanroom in the Black Hills State University cavern. Radiation shielding walls, doors, and mazes are next on the list!

Read More

Last Modified:


Crow Peak Hall, Black Hills State University, Spearfish, SD 4/29/15

 – By

Precast bridge work underway at Crow Peak Hall.


Read More

Last Modified:


Little Wound School Track Kyle, South Dakota 4/16/15

 – By

Hahn Construction is almost done with the fill section of the track and working on the cut side.

Read More

Last Modified:


Crow Peak Hall, Black Hills State University, Spearfish, SD 3/24/15

 – By



Wing walls on the southeast side of the pedestrian bridge are complete and crews will now be moving to the northwest side.

Excavation has begun for the volleyball pit. DKC crews will begin installing volleyball poles, nets and boundary lines in conjunction with the sand placement.


Picture from the 4th floor of the building overlooking the BHSU campus and site activities. Work continues on the Amphitheater tiered concrete seating as well as the pedestrian bridge foundations and wing walls.   
 

Concrete terrace walls continue for the future amphitheater seating area.  

Read More

Last Modified:


Surgical Tower Addition, Ft. Meade, Sturgis, SD 3/6/15

 – By

The basement floor has been completed and work continues on the first slab on deck.



Read More

Last Modified:


Intake Structure Roof Netting, Garrison Dam, ND 2/23/15

 – By

The netting serves two purposes: it is designed to be debris netting to catch falling concrete debris from the wind damaged roof, it will also double as fall protection for the contractor whom replaces the damaged roof structure in the future.

Read More

Last Modified:


Crow Peak Hall, Black Hills State University, Spearfish, SD 2/13/15

 – By

Progress is being made on the exterior of the building as the masonry continues. Progress is being made on the exterior of the building as the masonry continues.
The pedestrian bridge footings are complete and work has started on the wing walls.

The pedestrian bridge footings are complete and work has started on the wing walls.
Footings are being formed on the Amphitheater area.
Footings are being formed on the Amphitheater area.

Work is continuing on the wing walls for the pedestrian bridge.


Work is continuing on the wing walls for the pedestrian bridge.

Read More

Last Modified:


RESPEC Interior Remodel, Rapid City, SD 2/6/2015

 – By

Interior Office and Bathroom renovation at Respec, Jet Dr. Rapid City.  All construction work is being coordinated around normal business activity.  The completion of the initial Mid-Level Bathroom stage one is on schedule for turn-over, enabling demo work to begin soon for the Upper Level Kitchen area.   


Read More

Last Modified:


Coca-Cola Administrative Area Renovation and Addition 1/19/15

 – By

The building envelope is enclosed sufficient enough to allow interior finish work to begin in certain areas of the project. Metal stud framing and gypsum wallboard continue to be installed as well as mechanical and electrical rough in work. Interior walls are being taped, textured, and painted. The curtain wall glass is schedule for arrival on the project the week of January 12th which will fully enclose the building addition upon installation.



Read More

Last Modified:


Surgical Tower Addition, Ft. Meade, Sturgis, SD 1/7/15

 – By

Foundation wall construction will be 100% complete next week.
 

Read More

Last Modified:


×